BMM Implementation Workflows (Phase 4)
Overview
Phase 4 (Implementation) workflows manage the iterative sprint-based development cycle using a story-centric workflow where each story moves through a defined lifecycle from creation to completion.
Key principle: One story at a time, move it through the entire lifecycle before starting the next.
Complete Workflow Context
Phase 4 is the final phase of the BMad Method workflow. To see how implementation fits into the complete methodology:
The BMad Method consists of four phases working in sequence:
- Phase 1 (Analysis) - Optional exploration and discovery workflows
- Phase 2 (Planning) - Required requirements definition using scale-adaptive system
- Phase 3 (Solutioning) - Technical architecture and design decisions
- Phase 4 (Implementation) - Iterative sprint-based development with story-centric workflow
Phase 4 focuses on the iterative epic and story cycles where stories are implemented, reviewed, and completed one at a time.
For a visual representation of the complete workflow, see: workflow-method-greenfield.excalidraw
Quick Reference
| Workflow | Agent | When | Purpose |
|---|---|---|---|
| sprint-planning | SM | Once at Phase 4 start | Initialize sprint tracking file |
| create-story | SM | Per story | Create next story from epic backlog |
| dev-story | DEV | Per story | Implement story with tests |
| code-review | DEV | Per story | Senior dev quality review |
| retrospective | SM | After epic complete | Review lessons and extract insights |
| correct-course | SM | When issues arise | Handle significant mid-sprint changes |
Agent Roles
SM (Scrum Master) - Primary Implementation Orchestrator
Workflows: sprint-planning, create-story, retrospective, correct-course
Responsibilities:
- Initialize and maintain sprint tracking
- Create stories from epic backlog
- Handle course corrections when issues arise
- Facilitate retrospectives after epic completion
- Orchestrate overall implementation flow
DEV (Developer) - Implementation and Quality
Workflows: dev-story, code-review
Responsibilities:
- Implement stories with tests
- Perform senior developer code reviews
- Ensure quality and adherence to standards
- Complete story implementation lifecycle
Story Lifecycle States
Stories move through these states in the sprint status file:
- TODO - Story identified but not started
- IN PROGRESS - Story being implemented (create-story → story-context → dev-story)
- READY FOR REVIEW - Implementation complete, awaiting code review
- DONE - Accepted and complete
Typical Sprint Flow
Sprint 0 (Planning Phase)
- Complete Phases 1-3 (Analysis, Planning, Solutioning)
- PRD/GDD + Architecture complete
- V6: Epics+Stories created via create-epics-and-stories workflow (runs AFTER architecture)
Sprint 1+ (Implementation Phase)
Start of Phase 4:
- SM runs
sprint-planning(once)
Per Epic:
- Epic context and stories are already prepared from Phase 3
Per Story (repeat until epic complete):
- SM runs
create-story - DEV runs
dev-story - DEV runs
code-review - If code review fails: DEV fixes issues in
dev-story, then re-runscode-review
After Epic Complete:
- SM runs
retrospective - Move to next epic
As Needed:
- Run
sprint-statusanytime in Phase 4 to inspect sprint-status.yaml and get the next implementation command - Run
workflow-statusfor cross-phase routing and project-level paths - Run
correct-courseif significant changes needed
Key Principles
One Story at a Time
Complete each story's full lifecycle before starting the next. This prevents context switching and ensures quality.
Quality Gates
Every story goes through code-review before being marked done. No exceptions.
Continuous Tracking
The sprint-status.yaml file is the single source of truth for all implementation progress.
(BMad Method / Enterprise)
PRD (PM) → Architecture (Architect)
→ create-epics-and-stories (PM) ← V6: After architecture!
→ implementation-readiness (Architect)
→ sprint-planning (SM, once)
→ [Per Epic]:
→ story loop (SM/DEV)
→ retrospective (SM)
→ [Next Epic]
Related Documentation
Troubleshooting
Q: Which workflow should I run next?
A: Run workflow-status - it reads the sprint status file and tells you exactly what to do. During implementation (Phase 4) run sprint-status (fast check against sprint-status.yaml).
Q: Story needs significant changes mid-implementation?
A: Run correct-course to analyze impact and route appropriately.
Q: Can I work on multiple stories in parallel? A: Not recommended. Complete one story's full lifecycle before starting the next. Prevents context switching and ensures quality.
Q: What if code review finds issues?
A: DEV runs dev-story to make fixes, re-runs tests, then runs code-review again until it passes.
Phase 4 Implementation - One story at a time, done right.