workflow:
|
|
id: sprint-execution
|
|
name: Sprint-Based Development Workflow
|
|
description: >-
|
|
Agent workflow for sprint-based agile development. Handles sprint planning,
|
|
daily development cycles, mid-sprint adjustments, sprint reviews, and retrospectives.
|
|
Integrates Memory Bank updates and continuous documentation.
|
|
type: sprint
|
|
project_types:
|
|
- agile-development
|
|
- scrum-sprint
|
|
- iterative-delivery
|
|
- continuous-improvement
|
|
|
|
sequence:
|
|
- step: sprint_kickoff
|
|
agent: bmad-master
|
|
action: initialize_sprint_context
|
|
uses: session-kickoff
|
|
notes: |
|
|
Sprint initialization:
|
|
- Review Memory Bank for project state
|
|
- Check previous sprint outcomes
|
|
- Review product backlog
|
|
- Understand technical context
|
|
- Review team velocity and capacity
|
|
|
|
- agent: sm
|
|
action: sprint_planning
|
|
creates: sprint-plan.md
|
|
uses: sprint-planning-tmpl
|
|
notes: |
|
|
Sprint planning session:
|
|
- Define sprint goals
|
|
- Select stories from backlog
|
|
- Estimate story points
|
|
- Assign initial priorities
|
|
- Create sprint backlog
|
|
- Document in sprint-plan.md
|
|
|
|
- agent: po
|
|
validates: sprint_plan
|
|
action: approve_sprint_scope
|
|
notes: |
|
|
Validate sprint plan:
|
|
- Confirm goals align with product vision
|
|
- Verify story selection
|
|
- Approve priorities
|
|
- Sign off on sprint commitment
|
|
|
|
- daily_development_cycle:
|
|
repeats: for_each_sprint_day
|
|
sequence:
|
|
- agent: sm
|
|
action: daily_standup
|
|
creates: daily-status.md
|
|
notes: |
|
|
Daily coordination:
|
|
- Review yesterday's progress
|
|
- Plan today's work
|
|
- Identify blockers
|
|
- Update sprint burndown
|
|
|
|
- agent: dev
|
|
action: implement_daily_work
|
|
updates: implementation_files
|
|
notes: |
|
|
Development work:
|
|
- Work on assigned stories
|
|
- Follow coding standards
|
|
- Create unit tests
|
|
- Update story status
|
|
|
|
- agent: dev
|
|
creates: dev_journal_entry
|
|
action: document_daily_progress
|
|
uses: create-dev-journal
|
|
condition: end_of_day
|
|
notes: |
|
|
Daily documentation:
|
|
- Document work completed
|
|
- Note challenges faced
|
|
- Record decisions made
|
|
- Update Memory Bank activeContext
|
|
|
|
- step: mid_sprint_check
|
|
agent: sm
|
|
action: assess_sprint_health
|
|
condition: sprint_midpoint
|
|
notes: |
|
|
Mid-sprint assessment:
|
|
- Review burndown chart
|
|
- Assess story completion rate
|
|
- Identify at-risk items
|
|
- Plan adjustments if needed
|
|
|
|
- agent: po
|
|
action: mid_sprint_adjustment
|
|
condition: scope_change_needed
|
|
optional: true
|
|
notes: |
|
|
Sprint adjustment:
|
|
- Review proposed changes
|
|
- Approve scope modifications
|
|
- Update sprint goals if needed
|
|
- Communicate changes
|
|
|
|
- agent: qa
|
|
action: continuous_testing
|
|
updates: test_results
|
|
repeats: as_stories_complete
|
|
notes: |
|
|
Ongoing quality assurance:
|
|
- Test completed stories
|
|
- Report issues immediately
|
|
- Verify acceptance criteria
|
|
- Update story status
|
|
|
|
- agent: architect
|
|
creates: adr.md
|
|
action: document_decisions
|
|
condition: architectural_decision_made
|
|
notes: |
|
|
ADR creation:
|
|
- Document significant decisions
|
|
- Record context and rationale
|
|
- Update Memory Bank systemPatterns
|
|
- Link to related stories
|
|
|
|
- step: sprint_review_preparation
|
|
agent: sm
|
|
action: prepare_review_materials
|
|
creates: sprint-review-prep.md
|
|
condition: sprint_final_day
|
|
notes: |
|
|
Review preparation:
|
|
- Compile completed stories
|
|
- Prepare demonstration materials
|
|
- Document impediments
|
|
- Calculate velocity metrics
|
|
|
|
- agent: sm
|
|
action: conduct_sprint_review
|
|
uses: conduct-sprint-review
|
|
creates: sprint-review-summary.md
|
|
notes: |
|
|
Sprint review meeting:
|
|
- Demonstrate completed work
|
|
- Gather stakeholder feedback
|
|
- Document acceptance status
|
|
- Update product backlog
|
|
- Use sprint-review-checklist.md
|
|
|
|
- agent: po
|
|
action: accept_sprint_deliverables
|
|
validates: completed_stories
|
|
notes: |
|
|
Sprint acceptance:
|
|
- Review demonstrated features
|
|
- Confirm acceptance criteria met
|
|
- Sign off on completed work
|
|
- Update story status to Done
|
|
|
|
- agent: sm
|
|
action: sprint_retrospective
|
|
creates: sprint-retrospective.md
|
|
notes: |
|
|
Sprint retrospective:
|
|
- What went well
|
|
- What could improve
|
|
- Action items for next sprint
|
|
- Team velocity analysis
|
|
- Process improvements
|
|
|
|
- agent: bmad-master
|
|
action: update_memory_bank
|
|
uses: update-memory-bank
|
|
notes: |
|
|
Comprehensive Memory Bank update:
|
|
- Sprint outcomes to progress.md
|
|
- Technical decisions to systemPatterns.md
|
|
- Learnings to activeContext.md
|
|
- Update project velocity metrics
|
|
|
|
- workflow_end:
|
|
action: sprint_complete
|
|
notes: |
|
|
Sprint completed!
|
|
- All deliverables accepted
|
|
- Memory Bank updated
|
|
- Retrospective documented
|
|
- Ready for next sprint planning
|
|
|
|
flow_diagram: |
|
|
```mermaid
|
|
graph TD
|
|
A[Start: Sprint] --> B[bmad-master: sprint kickoff]
|
|
B --> C[sm: sprint planning]
|
|
C --> D[po: approve sprint scope]
|
|
|
|
D --> E[Daily Cycle Start]
|
|
E --> F[sm: daily standup]
|
|
F --> G[dev: implement work]
|
|
G --> H[dev: daily journal]
|
|
H --> I{More days?}
|
|
I -->|Yes| E
|
|
I -->|No| J[sm: mid-sprint check]
|
|
|
|
J --> K{Adjustment needed?}
|
|
K -->|Yes| L[po: scope adjustment]
|
|
K -->|No| M[Continue development]
|
|
L --> M
|
|
|
|
M --> N[qa: continuous testing]
|
|
N --> O{Architecture decision?}
|
|
O -->|Yes| P[architect: create ADR]
|
|
O -->|No| Q[sm: prepare review]
|
|
P --> Q
|
|
|
|
Q --> R[sm: sprint review]
|
|
R --> S[po: accept deliverables]
|
|
S --> T[sm: retrospective]
|
|
T --> U[bmad-master: update Memory Bank]
|
|
U --> V[Sprint Complete]
|
|
|
|
style V fill:#90EE90
|
|
style B fill:#FFE4B5
|
|
style C fill:#FFE4B5
|
|
style R fill:#ADD8E6
|
|
style T fill:#F0E68C
|
|
style U fill:#DDA0DD
|
|
```
|
|
|
|
decision_guidance:
|
|
when_to_use:
|
|
- Team follows agile/scrum methodology
|
|
- Fixed-length iterations preferred
|
|
- Regular stakeholder reviews needed
|
|
- Continuous improvement focus
|
|
- Multiple stories per iteration
|
|
|
|
handoff_prompts:
|
|
kickoff_to_planning: "Sprint context initialized. Ready for sprint planning with backlog items."
|
|
planning_to_po: "Sprint plan created with {{story_count}} stories totaling {{story_points}} points. Please review and approve."
|
|
daily_standup: "Yesterday: {{completed_tasks}}. Today: {{planned_tasks}}. Blockers: {{blockers}}."
|
|
mid_sprint_alert: "Sprint health check: {{completion_percentage}}% complete. {{at_risk_count}} stories at risk."
|
|
review_ready: "Sprint review prepared. {{completed_stories}} stories ready for demonstration."
|
|
retrospective_complete: "Sprint retrospective complete. {{improvement_actions}} action items for next sprint."
|
|
complete: "Sprint {{sprint_number}} complete. Velocity: {{velocity}} points. Ready for next sprint planning."
|